Facility & Available Dates
In collaboration with leading experts across the greenhouse industry, Niagara Propagators’ 17-acre facility was designed to optimize growing conditions, efficiency, and cleanliness. Breaking ground in November 2024, production begins January 2026.
January 2026
Production Begins
June 2025: Glazing, glazing, glazing.
April 2025: Superstructure takes to the sky.

February 2025: Materials start to arrive on site.

November 2024: Ponds, which will be used to collect and recycle rainwater, begin to take shape.


May 2025: Superstructure nearing completion.

March 2025: Cistern construction begins.

December 2024: Forming for the foundation walls.

October 2024: Niagara Propagators breaks ground

August 2025: A summer of pouring floors.

September 2025: Equipment arrives.


October 2025: Utilities are connected
November 2025: Overhead work in the grow areas near completion.