Facility & Available Dates

In collaboration with leading experts across the greenhouse industry, Niagara Propagators’ 17-acre facility was designed to optimize growing conditions, efficiency, and cleanliness. Breaking ground in November 2024, production begins January 2026.

January 2026

Production Begins

June 2025: Glazing, glazing, glazing.

April 2025: Superstructure takes to the sky.

February 2025: Materials start to arrive on site. 

November 2024:  Ponds, which will be used to collect and recycle rainwater, begin to take shape. 

May 2025: Superstructure nearing completion.

March 2025: Cistern construction begins.

December 2024: Forming for the foundation walls. 

October 2024: Niagara Propagators breaks ground

Groundbreaking - October.jpg

August  2025: A summer of pouring floors.

September  2025: Equipment arrives. 

October 2025: Utilities are connected

November  2025: Overhead work in the grow areas near completion.